Road Closure report 2/27/17
Please take a moment to visit our local sponsors to let them know that you appreciate their support of our blog.
advertise your local business here »It's Monday Morning and time for this weeks road report. Please note any closures not listed are permanent closures per the NCDOT
China Grove
I-85, Mile Marker 61 to 68, Heading North
Near NC-152 (NC-152)
Road Closed with Detour - Expected Impact to traffic is High
Start Time
3/15/2017 12:00 AM
End Time
3/18/2017 06:00 AM
Lane Construction will be closing northbound I 85 between exits #63 (Lane St.) and #68 (China Grove / U S 29/ N C 152) to remove the existing NC 152 bridge over I 85.
China Grove
I-85, Mile Marker 70 to 63, Heading South
Near NC-152 (NC-152)
Road Closed with Detour - Expected Impact to traffic is High
Start Time
2/23/2017 12:00 AM
End Time
3/1/2017 06:00 AM
Lane Construction will be closing southbound I 85 between exits #63 (Lane St.) and #68 (China Grove / U S 29/ N C 152) to remove the existing Lentz Road bridge over I 85.
China Grove
I-85, Mile Marker 70 to 63, Both Directions
Near NC-152 (NC-152)
Lane Closed - 1 of 2 lanes closed.
Expected Impact to traffic is Low
Start Time
6/20/2016 09:00 PM
End Time
6/30/2019 05:00 PM
The Contractor will need to have nightly lane closures along I-85 to preform investigation work for the upcoming I-85 widening project. Closures can take place in the inside or in the outside lane. Closures could be located on North Bound or South Bound I-85.
East Spencer
I-85, Mile Marker 84 to 83, Heading South
Near SR-2120 (SR-2120)
Lane Closed - 1 of 4 lanes closed.
Expected Impact to traffic is Low
Start Time
2/24/2017 08:00 AM
End Time
3/3/2017 04:00 PM
Maintenance of spill basins
Landis
SR-1210, Heading South
Near US-29 (US-29)
Lane Closed - 1 of 2 lanes closed.
Expected Impact to traffic is Low
Start Time
10/20/2014 09:00 AM
End Time
5/31/2017 05:00 PM
China Grove
SR-1243 (Daughtery Rd), Both Directions
Near SR-1337 (SR-1337)
Road Closed with Detour - Expected Impact to traffic is High
Start Time
1/21/2017 06:00 AM
End Time
8/9/2017 05:00 PM
The Daugherty Road bridge over I-85 is being replaced as part of the I-85 widening project.
China Grove
SR-1337 (Lentz Road), Both Directions
Near US-29 (US-29)
Road Closed with Detour - Expected Impact to traffic is High
Start Time
2/13/2017 06:00 AM
End Time
9/1/2017 05:00 PM
The Lentz Road bridge over I 85 is being replaced as part of the I 85 widening project.
China Grove
SR-1505 (Mt. Hope Church Road), Both Directions
Near US-29 (US-29)
Road Closed - Expected Impact to traffic is High
Start Time
2/23/2015 07:00 AM
End Time
1/27/2018 01:24 PM
As part of the Railroad Improvement Projects the railroad crossing on Mt. Hope Church Road is Permanently closed.
Salisbury
SR-1526 (Henderson Grove Church Rd), Both Directions
Near US-29 (US-29)
Road Closed with Detour - Expected Impact to traffic is High
Start Time
1/25/2017 08:30 AM
End Time
5/31/2017 12:00 AM
Replace the existing the Henderson Grove Church Road Bridge and Begin work on January 25, 2017@ 9:00 am and complete by end of May 2017
Rowan CountySR-1986 (Mt Vernon Rd), Both Directions
Near SR-1986 (SR-1986)
Road Closed with Detour - Expected Impact to traffic is High
Start Time
3/13/2017 09:00 AM
End Time
9/30/2017 12:00 AM
Road Closed to replace the existing bridge to box culvert
Rockwell
SR-2140 (St. Matthews Church Road), Both Directions
Near SR-2142 (SR-2142)
Lane Closed - 1 of 2 lanes closed.
Expected Impact to traffic is Low
Start Time
11/18/2014 11:48 AM
End Time
12/31/2017 12:48 PM
The causeway of St. Matthews Church Road across High Rock Lake is closed to two way traffic and commercial vehicles.