Latest DOT Road Closures around the County 2/13/2017

Monday, February 13, 2017 - 9:05am

Please see the closures below. If there is not a closure listed it is either not mentioned by the NCDOT at this time or is a permanent road closure.

 

85 North China Grove through February 23rd 2017

Night Time Construction: Road Closed with Detour

 Lane Construction will be closing northbound I 85 between exits #63 (Lane St.) and #68 (China Grove / U S 29/ N C 152) to remove the existing Lentz Road bridge over I 85.

 

85 South China Grove through March 1st 2017

Night Time Construction: Road Closed with Detour

 Lane Construction will be closing southbound I 85 between exits #63 (Lane St.) and #68 (China Grove / U S 29/ N C 152) to remove the existing Lentz Road bridge over I 85.

 

Landis through May 31st 2017

 South Central Ave. will be closed to Southbound traffic from Mill St to Hillside St. Starting 9:00 am on October 20, 2014 until further notice

China Grove through August 9th 2017

The Daugherty Road bridge over I-85 is being replaced as part of the I-85 widening project.

China Grove through September 1st 2017

 The Lentz Road bridge over I 85 is being replaced as part of the I 85 widening project

Salisbury through May 31st 2017

 Replace the existing the Henderson Grove Church Road Bridge and Begin work on January 25, 2017@ 9:00 am  and complete by end of May 2017.

Rockwell through December 31st 2017

 The causeway of St. Matthews Church Road across High Rock Lake is closed to two way traffic and commercial vehicles.

 